|
This task shows you how to display the Gantt Chart viewer. |
|
A Gantt chart allows users to do a basic, overall
cycle-time analysis for a set of actions. The Gantt chart visualization is
based on the cycle time parameter defined in each action. The Gantt chart
is another way to visualize your sequence. Note that you cannot modify the
action duration using the Gantt window. A Gantt chart is bar graph of a
sequence. It shows start and stop times as well as dependencies.
The Gantt chart is a 2D view of the sequence process. |
|
Open the
CHAINSAWAT.CATProduct document which has a sequence defined. |
|
-
Select a sequence in the specification tree, e.g.,
Sequence.4.
|
|
You cannot see multiple sequences in a single Gantt chart. |
-
Select Window > New Gantt Chart Window.
|
The Gantt chart window is displayed: |
|
- The left frame of the Gantt chart lists each of the individual
actions and /or analyses that exist in your document, displaying
the duration, start time, and end time for each.
- The right frame provides a graphical representation of each
action or analysis (along the line of time), and also indicates the
start, duration and end of each.
- A dashed vertical line in the right window (called the Time
Line), provides a visual indication of the current time during the
execution.
|
-
Click OK on the Edit Sequence
dialog box and close the Gantt chart viewer.
|
|
Altering the Duration of an Action
|
|
-
On the specification tree, double-click on a sequence.
The Edit Sequence dialog box appears. |
-
Select Window > New Gantt Chart Window.
The Gantt chart window appears. |
-
Alter the duration of the track by stretching the
graphical representation on the right side of the Gantt chart.
The duration shown in the Edit Sequence dialog box
takes on the new value. |
-
Alter the duration of the track by changing the duration
within the Action duration field of the Edit
Sequence dialog box.
The duration shown in the Gantt chart takes on the new value. |
|