This task shows you how to transfer
elements in your layout from one level of the specifications tree to
another.
1.
Make the appropriate element
active.
You must make active
an element that is at least one level higher than both the source element
(i.e., the one that is being transferred) and the target element.
For example, in order to transfer
ArrBox5, ArrBox6, ArrBox7, ArrBox 8, and ArrBox9 to ArrArea3, shown below,
ArrArea1 or Product1 must be active.
2.
Select the elements you want to
transfer.
3.
Select the Transfer Elements
in Tree button
.
4.
Select the element to which you
want the elements transferred.
The target element must also be a
child of the active element.
The elements you select in Step 2
become children of (i.e., subordinate to) the element you select in Step 4.