Tolerance analysis is computed from assembly process
activities. The assembly process is made of a set of only four activity types: Positioning, Fastening, Already Done Fastening and Release. Activities must be linked to each other and items assigned to define the activity. Process activities may be a combination of linear and/or parallel sequences. |
|
![]() |
Add an Activity: Click this icon, select the process. |
![]() |
Add an Activity: Click this icon, select the process. |
![]() |
Add an Activity: Click this icon, select the process. |
![]() |
Add an Activity: Click this icon, select the process. |
![]() |
Link Activities: Click this icon, select the activities. |
![]() |
Manage Items: Click this icon, select an item then select the activity. |
![]() |
Manage Items Click this icon, select the activity then select the items. |